234             蔡進雄  朱旭   徐展賦  軌道工程施工看施工管理之探討─以南港線東延段為例





                 A Review of Trackwork Construction Management on Nangang Eastern
                                                       Extension

                                                     1
                                                                      2
                                Chin-Hsiung Tsai   Daniel H. Ju   Chan-fu Hsu           3
                                                       Abstract
                 Taipei MRT Nangang eastern extension Phase 1, from Kunyang Station to Nangang Station, is

            scheduled to open for commercial service by the end of 2008. The trackwork is a major part of MRT
            contruction projects and also plays a critical role in determining if the project will be completed
            successfully and begin operation on time. The trackwork for the Nangang eastern extension only
            began in Aug. 2007. Restricted by limited time and a complicated construction site, where the

            construction of the main structure and cut and cover section (including double crossover, departure
            and arrival work shaft) are ongoing concurrently, the responsible engineers have been making
            great endeavors to push construction forward to meet the completion target date and then hand
            over the project to the Electrical and Mechanical contractor in accordance with the stipulations of

            the contract. Under high pressure due to the limited construction period of only seven months, the
            engineers have virtually created the chance to advance revenue service and also provided high-
            quality MRT construction for the citizens of Taipei City.
                 Owing to a lack of manpower and equipment, a delayed construction start and the urgency

            of the work schedule, the contractor subcontracted the trackwork and relevant work to a fully
            experienced contractor who was previously commissioned to implement the trackwork of the
            Tucheng line. The subcontractor first made improvements to construction equipment and facilities
            based on the construction characteristics, so as to promote work efficiencies and shorten the

            construction period. With well-arranged construction planning, full implementation, and well-
            utilized manpower the trackwork was carried out at full speed and completed on schedule. During
            the whole process of construction, the trackwork subcontractor pushed the work forward in a very
            positive manner, broke through traditional construction method constraints and created a number

            of benefits for this project. Therefore, it is expected that the successful experience of trackwork of
            Nangang eastern extension will be applied in future MRT line construction and result in enhanced
            service quality for Taipei's citizens.



            Key words: construction route,construction planning, Sub-contractor