Page 194 - 捷運技術 第38期
P. 194

188              莊建忠 葛博淵 無震動低噪音鑽石鏈鋸工法應用於營運介面連續壁破除




                  無震動低噪音鑽石鏈鋸工法應用於營運介面連續壁破除




                                                 莊建忠   葛博淵             2
                                                           1
                                                          摘要

                 捷運新莊線CK570A區段標 [ 忠孝新生站 (O13/BL9) ] 新建工程與營運中南港線忠孝新生
             站 (BL9) 交會,在進行結構體連通施工於已營運車站既有連續壁敲除作業進行時,因連續壁
             內埋有密集之巨大H型鋼,若採用傳統之機具直接敲除作業,則將造成營運車站有噪音、粉
             塵及振動等環境污染,影響民眾搭乘捷運之品質,甚或可能因振動之傳遞,影響捷運系統監
             測儀器之判讀,造成停駛之危機。

                 本文就臺北捷運工程第一次引進使用之重型切割系統『鑽石鍊鋸切割工法』施工經驗分
             享,並提供未來捷運工程在已營運車站大範圍施工做為參考以確保民眾搭乘捷運之品質及安
             全達成安全、快速、無污染之目的。

             關鍵詞:交會車站、鑽石鍊鋸、切割工法


                Adoption of Diamond Chain Cutting Method for Demolishment of Existing

                                                   Diaphragm Wall

                                                          1
                                            Steve Juang   Bo-Yuan Ger        2


                                                        Abstract
                 The Xinzhung line's contract CK570A, which is under construction, will meet the Nangang
             line where Zhongxiao Xinsheng Station is already in operation. Due to the existing diaphragm wall

             having huge H-Beams distributed densely throughout, if traditional demolition methods were used
             on the existing structure it may bring about non-environmentally friendly pollution, such as noise,
             dust, vibration etc, which could impact on the service quality of the MRT, or even worse, it may
             interfere with system monitoring instruments and lead to the system's shutdown.

                 This article introduces the“Diamond Chain Cutting System”initially adopted in the
             construction of the Taipei MRT, and shares construction experience for future MRT construction
             implementation on stations currently in operation, in anticipation that the construction method can
             contribute to ensuring the general public's safety so as to reach the goal of building a safe, fast and

             environmentally-friendly MRT system.
             Keywords: intersectional station, Diamond Chain Cutting method










            1 臺北市政府捷運工程局南區工程處工務所主任                                steve@trts.dorts.gov.tw
            2 中華工程公司 捷運新莊線CK570A區段標專案經理                           GBY@ms96.url.com.tw