捷運技術        第 50 期                                     137


                            綠色松山線貫通、臺北捷運路網大功告成


                                                          1
                                                                        2
                                                曾昭容     方仁鳳


                                                          摘要

                 2014 年是臺北捷運最值得歡慶的一年,11 月 15 日松山線通車,完成臺北市中心區捷運
            格狀路網的最後一塊拼圖,結束各路線跨線運行的過渡模式,整併回歸至原整體路網「棕、

            紅、綠、橘、藍」5 條線,安全、大運量及速捷的專線營運服務,透過多點轉乘,可方便迅
            速地抵達目的地,縮短都會的距離,擴大臺北生活圈域,而松山線為臺北市第三條東西向捷
            運線,其完工除對捷運路網之完整性別具里程碑意義外,松山線可謂所有捷運路線中施工複
            雜度最高、挑戰最嚴峻者,施工期間更特別考量古蹟維護與提升建築美感。


            關鍵詞:捷運路網、松山線


                Opening of the Songshan Line Contributes to a Complete

                                            Taipei MRT Network


                                                                                  2
                                      Tseng, Chao-Jung     1   Fang, Zen-Fung



                                                       Abstract

                 2014 was a banner year for the Taipei MRT. With opening of the Songshan line on November
            15,  the  last  major  puzzle  piece  of  the  downtown  Taipei  MRT  network  was  completed.  The
            grid-shaped  system  was  organized  into  five  lines  distinguished  by  color:  Brown,  Red,  Green,
            Orange, and Blue. Through multiple transfer points, users enjoy more convenient, comfortable and

            rapid MRT travel. Shortened travel times enhance ride quality. Being the third east-west MRT route
            in  Taipei,  the  inauguration  of  the  Songshan  line  marked  an important  milestone  for  a
            comprehensive MRT network. In addition, the Songshan line was one of the challenging lines to
            construct in the Taipei MRT project due to the strong emphasis placed on historic relic preservation

            and architectural aesthetics.

            Keywords: MRT network, Songshan Line












            1 臺北市政府捷運工程局綜合規劃處正工程司                           ccj@trts.dorts.gov.tw
            2 臺北市政府捷運工程局綜合規劃處第一課課長                          e1011006@trts.dorts.gov.tw
   136   137   138   139   140   141   142   143   144   145   146