Page 88 - 捷運技術 第56期
P. 88

Journal of Rapid Transit System and Technology No.56
            pp. 77-102, 2021                                  DOI 10.29670/JRTST.202110_(56).0005




            Received May 28, 2020, accepted July 09, 2020, date of publication October 31, 2021




                 BIM-4D for MRT Design and Construction
                                              Projects




            CHINHUNG TSENG , MINWEN SHIH , CHIHWEI CHUANG
                                                                   2
                                               1
                               1
            1  Engineer, Mass Transit Engineering Department, Sinotech Engineering Consultants, Inc.
            2  Technical Manager, Mass Transit Engineering Department, Sinotech Engineering Consultants, Inc.
            Corresponding authors: CHINHUNG TSENG, E-mail: chin-hung@mail.sinotech.com.tw


                                              ABSTRACT


            BIM-4D is utilized to integrate BIM-3D models with construction schedules in
            order to achieve project implementation sequence visualization. By importing
            schedules into the design phase, scheduling engineers are involved in the BIM
            creation process to integrate the design model with the overall schedule. Therefore,
            for subsequent changes in project schedules or models, BIM-4D not only can be
            utilized to review critical path changes and monitor milestones in real time, but also
            be applied for project management.


            During the implementation of BIM-4D, the most complicated part is finding
            methods of quickly and efficiently incorporating the BIM-3D model with the
            construction schedule. This study discusses the production of BIM-3D components
            and the planning of schedules, then develops a labor-saving and friendly
            operational mode. Moreover, it demonstrates the utilization of Synchro PRO, a
            software program which is widely used abroad, to perform BIM-4D operations.

            This study utilized BIM-4D to simulate the elevated and underground sections
            during the design stage of the MRT project. For the deep excavation of
            underground stations and the route structure of the elevated sections, BIM-4D was
            applied to create the related working schedules for critical path changes and the
            arrangement of different activities. Meanwhile, BIM-4D can be employed to
            effectively identify whether or not scheduling rearrangements will affect milestones
            during the construction process when obstacles are encountered or the delivery of
            land is delayed. It strengthens the control of the project schedule.


            Keywords:  BIM-3D, BIM-4D, Schedule Management