Page 123 - 捷運技術 第54期
P. 123
半圓形全套管擋土樁—臺中捷運深開挖擋土工法之革新精進案
Line Construction Project of Co-construction of Entrance and Joint
Development Supervision Execution Plan, United Steel Enterprises
Company, Kaoshiung, 2016. in Chinese.
9. Li-Ting Hsu, Yuan-Yao Tsai, Hung-Kuei Teng, Chia-Jui Chen and
Ching-Lin Wang, “Case study of Taichung Rapid Transit System
Construction Project of Joint Development Building - Challenges and
Breakthroughs in Deep Excavation in Taichung Metropolitan Area”
, The deep excavation design and construction seminar of Taichung
Rapid Transit System Wurih-Wenxin-Beitun Line Construction
Project, 29 June, Taipei, 56-64, 2017. In Chinese.
10. Council of Labor Affairs, Executive Yuan, Discussion on the safety
of excavation in the gravel area, Council of Labor Affairs, Executive
Yuan, Taipei, 1997. In Chinese.
121