                                                          摘要
                   ઠ༶อ୿ᘻݲᇞуਗ਼׵ϋ(99)ֵۃஷԓd࠽Ϥʘყdतй዆ଣ̈อ୿ᇞΌݬʿᘻݲᇞ

              ༰ՈϞतЍʘ݄ʈʈج(ࠇ11ධ)dࡏᔊʧՉ݄Ъཀ೻f຾ઞীdவԬʈجમٙ͜ଣ͟dʔ
              ̮˷݊މəд؂ઽช׌ήᄴeτΌ߈൳ήɨ࿬Ϟഐ࿴يeಯˇմቊʹஷላᏘeࠥЭᅂᚤ
              ቌגࠬᎈe౤৷݄ʈࣖଟ˸ʿື޲຾൬nഃഃdίཀ̘9ϋԸ݄ٙʈཀ೻ʕdޟЇϞʔˇ
              ධͦ௴ɨə਷ʫʈ೻ޢ࠯Էf͉˖ϙί౤Զ݄ʈ຾᜕Ϋ㉿ၾܔᙄdಂঐڮආܝᚃઠ༶༩

              ᇞʘၚආe௴อЪމf
              ᗫᒟ൚j  ଉකܱe༸ҋe၍࿇eԣ˥ཞጵeήᒞeɧࠠ၍৷Ꮐᄝ࢛ᙺᆉ(RJP)eиࡖʈ
                         جe৵๊၍eᏀɝόήᒞӐᇌ



               Construction Methods and Processes of the Xinzhuang & Luzhou Line’ Civil Engineering
                   Chi-Ning Sun  Wei Lee  Hung-Kun Ku  Lian-Chih Chen  Steve Juang

                      Rong-Fong Jhan  Min-Hsiang Huang  C.H. Chen  Paul,P.S. Tsuei

                      Shih-I Cheng  Yi-Chin Chiu  Lian-Shian Chen  Chung-Che Tsao

                                                       Abstract

                   A section of the Xinzhuang & Luzhou line is scheduled to begin commercial service
               before the end of 2010. On this occasion, a total of 11 characteristic construction methods
               applied to the entire Xinzhuang line and the Luzhou line have been organized for the purpose

               of introducing their construction process. After review, we realize that, unsurprisingly, the
               reasons for adopting these construction methods are to overcome sensitive stratum, minimize
               the impact on surrounding traffic flow, lower the risk of affecting buildings along the MRT

               routes, enhance construction efficiency, reduce costs, etc. In the past nine years of construction,
               a number of techniques have been used for the first time in the nation. This article aims to
               provide construction experiences and suggestions with the hope of creating enhancement and
               innovation on future routes.
               Keywords: deep excavation, turnout structure, pipe screen, flood gate, ground anchor,

                                     Rodin Jet Pile(RJP), Freezing Method, Tube-A-Manchette, hydro pressure anchor
                                    caisson